c. Review EVE IWG roadmap, Next Steps
Using document EVE-06-03e, Revised EVE Roadmap – May 2013, the Secretary went over the key dates and deadlines. The first draft of the Reference Guide will be reviewed by the EVE IWG at the EVE-7 meeting in Beijing, China (October 17 – 18, 2013), a revised second draft of the Guide will be submitted to the GRPE for first review at the January 2014 session and approval at the GRPE session in June 2014, with the goal of submitting the Guide in August 2014 for WP.29 approval at the November 2014 session. A comment was noted by OICA that the date in item 3.8 needs to be changed from October 2012 to October 2013; the date in item 4.0 also needs to be adjusted to January 2014.
ACTION 9: The Secretary will revise and post the revised version of document EVE-06-03e.