Document Title WLTP-DHC next actions schedule
Reference Number WLTP-DHC-09-06
Date
18 Jul 2011
Rulemaking Area(s) GTR No. 15 WLTP
Meeting(s)
Downloads
UNECE server .pdf format
Excerpts from session reports related to this document
WLTP-DHC | Session 9 | 6-7 Jul 2011

16. It was agreed that alternative Extra High speed phase proposals should be submitted by the 21st July and would be discussed by teleconference on 27th July. (later the date is changed to 26th July) Validation phase 1 will commence immediately after the teleconference. The next meeting of the group was scheduled for October. OICA requested that the meeting be hosted by JRC in Ispra, Mr Ichikawa agreed to discuss this with JRC.

Summary of Actions & Open Issues

Action 1, Chair: Agree unified database with Mr Steven, JRC and Ms Ericsson, inform group when this was done and upload unified distribution to CIRCA.

Action 2, OICA: Alternative proposals for distribution of idling periods to be submitted and considered after validation 1.

Action 3, validation 1 participants: Impact of initial idling duration on cold start, Low speed phase air pollutant emissions to be investigated during validation 1.

Action 4, Mr Steven: Alternative Extra High speed phase proposals to be provided by 21st July along with an explanation of the methodology used to derive them.

Action 5, Mr Steven: Alternative gearshift proposal to be submitted by end of July for evaluation during validation 1.

Action 6, OICA: To consider an alternative proposal on neutral and first gear selection points at 0 km/h

Action 7, Japan: To consider whether areas of microtransience/noise on the speed trace should be smoothed prior to the start of validation 1.