5.1 Performance requirements
In order to determine standpoints of the CPs that were present during the meeting, COM had prepared a list of basic performance requirements that shall formulate the technical framework of the GTR. Each of the requirements was briefly discussed. Subsequently, each CP gave its opinion which was noted in the list.
5.2 Test procedure
ISO gave an update on the development of test protocol SAE J2889-1/ISO 16254. As there are no substantial changes to the procedure, the presentation basically was a repetition of the one from the last meeting.
5.3 Other development of the draft GTR document
The Task Force focused on the text that was not discussed during the latest official meeting of the IG GTR for QRTV. In this manner, the text has been commented upon and suggestions with respect to the streamlining of the text have been recorded. The text in the linked document represents its latest status and will be the base for continued discussions during the following meeting.