Derivation of Draft FlexPLI prototype impactor limits
Document GTR9-06-08
11 March 2013
Submitted by BASt
Download document
Previous Documents, Discussions, and Outcomes
12.1. | Discussion on injury thresholds/criteria

Mr. Zander presented an overview on document GTR9-6-08. He pointed out that it is not the intention of BASt to change the injury criteria. Mr. Zander explained the process used at BASt to derive the threshold values and noted that his approach was slightly different than the approach of JAMA/JARI. He also highlighted the agreements made during the work of the former FlexPLI Technical Evaluation Group (TEG) on the FlexPLI thresholds. He concluded that, however, as both approaches were combined the impactor threshold values also depend on the actual performance of the latest impactor version and therefore should be adapted accordingly, if necessary.