Collective amendments to UN Regulations Nos. 3, 4, 6, 7, 19, 23, 27, 38, 50, 69, 70, 77, 87, 91, 98, 104, 112, 113, 119 and 123
Download in .pdf format Download in .docx format

SLR informal group removing the brackets around (i.e., confirming) the 24-month transition period for the switch to approvals only under the new LSD, RRD, and RID regulations and to delete the proposal that approvals and extensions of approvals granted under each regulation would remain valid indefinitely.

Reference Number: GRE/2018/34
Date: 9 August 2018
Proposal Status: Superseded
Related Documents:
GRE/2018/11 | Collective amendments to Regulations Nos. 3, 4, 6, 7, 19, 23, 27, 38, 50, 69, 70, 77, 87, 91, 98, 104, 112, 113, 119 and 123
WP.29/2018/91/Rev.1 | UN R3: Proposal for the 03 series of amendments
Discussion(s):
Working Party on Lighting and Light-signalling | Session 80 | 23-26 Oct 2018

9. GRE recalled that, at its previous session, it had provisionally adopted transitional provisions to “freeze” UN Regulations Nos. 3, 4, 6, 7, 19, 23, 27, 38, 50, 69, 70, 77, 87, 91, 98, 104, 112, 113, 119 and 123 (ECE/TRANS/WP.29/GRE/2018/11), with square brackets around the third transitional provision on the validity of existing type approvals, and had agreed to take a final decision at this session (ECE/TRANS/WP.29/GRE/79, paras. 11 and 17). The Secretary of IWG SLR presented the revised transitional provisions (ECE/TRANS/WP.29/GRE/2018/34) which propose the deletion of the third transitional provision for all concerned UN Regulations. The expert from OICA expressed concerns that this deletion might lead to different interpretation among type approval authorities and that some of them might question the validity of existing type approvals (GRE-80-21). GRE confirmed that the revised transitional provisions, as proposed in ECE/TRANS/WP.29/GRE/2018/34, do not affect the validity of type approvals already granted pursuant to the UN Regulations concerned.

10. Upon this understanding, GRE adopted ECE/TRANS/WP.29/GRE/2018/34 and requested the secretariat to submit it to WP.29 and AC.1 for consideration at their November 2018 sessions as corrigenda to the original SLR package. GRE also expressed a hope that, in spite of the late submission of these modifications, contracting parties would be in a position to take them into consideration and to vote for the complete updated SLR package in November 2018.