previous meeting next meeting
Teleconference
(Latest 15 July 2013)
1. Welcome and introductions
2. Approval of the minutes of the last meeting
LNG-10-04 | Draft minutes of the 10th LNG task force session
3. Automatic valve on the LNG tank
LNG-11-01 | Proposal to introduce automatic cylinder valve provisions into the LNG text for UN Regulation No. 110 Draft text under discussion within the LNG task force concerning automatic valve requirements on LNG tanks.
LNG-11-03 | Proposal to introduce automatic cylinder valve provisions into the LNG text for UN Regulation No. 110 Draft text under discussion within the LNG task force as of its 11th session proposing amendments to document GRSG/2013/7 concerning automatic valve provisions.
LNG-11-02 | Technical report on LNG tank shutoff valves Review of four international LNG standards (ISO 12991-2012, NFPA 52-2013, SAE J2343-2008 and AS 2739-2009) for requirements related to LNG tank shut-off devices. The report discusses specific aspects and challenges of mounting two valves in series on same LNG line. The emphasis is on using two components, a manual valve and an automatic valve mounted in series on the LNG supply line to shutoff the flow.
4. 80% fill stop on the LNG tank
5. LNG in use with ADR (dangerous goods) vehicles
6. Any other business
LNG-11-03 | Proposal to introduce automatic cylinder valve provisions into the LNG text for UN Regulation No. 110 Draft text under discussion within the LNG task force as of its 11th session proposing amendments to document GRSG/2013/7 concerning automatic valve provisions.